3701-31-04 (B)(1)(c) / Minimum disinfection residual shall be maintained as required.
Critical Chlorine disinfectant residual was less than 1 ppm for the pool
Do not operate the pool when the disinfectant residuals are less than what is required. Ensure the chlorine disinfectant residual is at 1 ppm or above prior to placing the pool back into operation.
3701-31-04 (B)(4)(a)(iv) / Water temperatures are recorded daily
Repeat Water temperatures were not being recorded daily.
Take and record the water temperature at least once/day.
3701-31-04 (B)(6)(f) / Required turnover rates are sufficient
Required turnover rates were not met.
Have the circulation system evaluated to determine why the turnover rates are not able to be met. Once the reasons have been determined have the issue repaired. If necessary, submit plans to the Ohio Department of Health to review and approve.
Facility Type: Pool
Inspection Type: Standard
Inspection Date: 23-July-2019
Comments |
---|
NO CHLORINE RESIDUAL AT TIME OF INSPECTION - NO CHLORINE IN CHLORINE TANK - OPERATING WITHOUT CHLORINE - POOL TO REMAINED CLOSED UNTIL CHLORINE IS DELIVERED TO FACILITY AND CHLORINE LEVELS ARE COMPLIANT |