[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (D)(7)(d) / Flow or pressure switch with a shut off valve shall be provided and tested monthly.
Critical Flow or pressure switch for a shut off valve was not tested monthly
Provide records indicating that the unit is being tested monthly. Correct By: 24-Jun-2023

3701-31-04 (B)(4)(a)(ii) / Combined chlorine is tested daily at pool side prior to use
Combined chlorine was not tested daily at pool side prior to use.
Test for combined chlorine prior to bathers entering the water and every 4 hours the pool is open for use. If ACC is in use combined chlorine must be tested every 12 hours while the pool is in use. For spraygrounds and spray features, the combined chlorine must be tested at 1 spray feature every 6 hours the sprayground or spray feature is in use. Correct By: 24-Jun-2023


Inspection Information


Facility Type: Pool

[?] Inspection Type: Standard

Inspection Date: 22-June-2023


Comments
The operator was observed performing onsite chemical tests

Our records show that the main drain suction outlet covers (AquaStar WAV 12 101) were installed 5-14-21. The covers have a 5 year life span and must be replaced before 5-14-26.