[?] A summary of the violations found during the inspection are listed below.

No critical violations were documented at the time of inspection.

No violations were documented at the time of inspection.


Inspection Information


Facility Type: Pool

[?] Inspection Type: Standard

Inspection Date: 22-June-2023

Comments
The acceptable flow rate for DE filters is 2 gpm/sq ft. The filter surface area should be double checked since the flow rate has increase significantly. Flow rates above 2 gpm/sq ft. can damage the filter.

Our records show that the main drain suction outlet covers (Lawson MLD-FGD-1212) were installed on 5-21-19. The covers have a 10 year life span and must be replaced before 5-21-29.

The operator was observed performing onsite chemical tests appropriately