[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (B)(6)(h) / Required meters and gauges maintained/functional
Required meters and gauges were not maintained or were not functional while the pool is in operation.
Maintain all meters and gauges in a properly functioning manner at all times while the pool is in operation. REPLACE THE PRESSURE AND VACUUM GAUGES ON THE JET PUMP. POST THE JET PUMP CURVE ALONG WITH THE CALCULATION FOR DETERMINING THE FLOW RATE Correct By: 09-Jul-2019
3701-31-04 (D)(7)(d) / Flow or pressure switch with a shut off valve shall be provided and tested monthly.
Critical Flow or pressure switch for a shut off valve was not provided or the unit was not tested monthly
Have the ACC unit serviced or replaced with a unit that has a flow or pressure switch with an automatic shut off valve. Provide records indicating that the unit is being tested monthly. REPAIR THE AUTOMATIC CHEMICAL CONTROLLER FLOW SWITCH IF NECESSARY. TEST/RECORD THE ACC MONTHLY. Correct By: 27-Jun-2019


Inspection Information


Facility Type: Spa

[?] Inspection Type: Standard

Inspection Date: 25-June-2019

Comments
Our records show: The main drain suction outlet cover (AquaStar WAV 12, WAV 9) was installed 5/18/2015. The cover has a 5 year life span and must be replaced before 5/18/2020.

-the spa was having maintenance work done at the time of the inspection. No water testing was done.