[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (B)(6)(b) / Replacement pipe is rigid PVC or the equivalent
The rubber coupling is used to joint two lengthens of pipe.
REPLACE THE RUBBER COUPLING WITH SOLID APPROVED PIPE. Correct By: 25-Jun-2017
3701-31-04 (B)(6)(c)(v) / Discharge of water from a public swimming pool shall be in accordance with OEPA.
The backwash drain to the sewer does not have a proper air gap.
INSTALL AN AIR GAP ON THE BACKWASH DISCHARGE LINE. REPEAT VIOLATION. Correct By: 26-May-2017
3701-31-04 (B)(6)(t) / Equipment/chemical/storage areas are free of hazards/accessible only to authorized personnel.
Critical The filter room was not locked.
TO KEEP CHEMICALS INACCESSIBLE, KEEP THE FILTER ROOM LOCKED. Correct By: 25-May-2017


Inspection Information


Facility Type: Pool

[?] Inspection Type: Follow-up

Inspection Date: 23-August-2017

Comments
POOL MAY REOPEN