[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (B)(6)(f) / Required turnover rates are sufficient
Repeat Required turnover rates were not met.
INCREASE FLOW RATE TO AT LEAST 54 GPM.
3701-31-04 (C)(3) / Total alkalinity is at or greater than 60 ppm
Repeat Total alkalinity was less than 60 ppm.
Raise the total alkalinity to at least 60 ppm. ADJUST ALKALINITY. Correct By: 02-May-2019


Inspection Information


Facility Type: Pool

[?] Inspection Type: Standard

Inspection Date: 29-April-2019