[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (B)(1)(e) / Automatic Chemical Controller (ACC) shall function properly.
Critical Automatic Chemical Controller (ACC) was not functioning properly at the time of the inspection.
Ensure that the ACC unit is functioning properly. REPAIR/REPLACE ACC SO THAT THE FLOW SWITCH SHUTS OFF CHEMICAL FEEDING WHEN THE FLOW IS STOPPED. FLOW SWITCH MAY NEED TO BE REPLACED. Correct By: 12-Jun-2022
3701-31-04 (B)(6)(f) / Required turnover rates are sufficient
Required turnover rates were not met.
Have the circulation system evaluated to determine why the turnover rates are not able to be met. Once the reasons have been determined have the issue repaired. If necessary, submit plans to the Ohio Department of Health to review and approve. INCREASE FLOW RATE TO 50 GPM. Correct By: 17-Jun-2022
3701-31-04 (B)(6)(i) / A means of determining rate-of-flow on all water pumps
A means of determining rate-of-flow was not found for all water pumps.
Properly install a flow meter or have a pump curve available for every water pump used for the pool. POST PUMP CURVE AND CALCULATION FOR THE JET PUMP. Correct By: 17-Jun-2022
3701-31-04 (C)(2) / pH is within 7.2 to 7.8
pH was outside the range of 7.2 to 7.8.
Treat the pool water so that the pH is within the acceptable range. ADJUST pH Correct By: 12-Jun-2022
3701-31-04 (D)(7)(d) / Flow or pressure switch with a shut off valve shall be provided and tested monthly.
Critical Flow or pressure switch for a shut off valve was not provided or the unit was not tested monthly
Have the ACC unit serviced or replaced with a unit that has a flow or pressure switch with an automatic shut off valve. Provide records indicating that the unit is being tested monthly. TEST AND RECORD FLOW SWITCH FUNCTION MONTHLY. Correct By: 12-Jun-2022


Inspection Information


Facility Type: Spa

[?] Inspection Type: Standard

Inspection Date: 10-June-2022

Comments
THE SPA HAS A SVRS, BUT NOT SURE THAT IT REQUIRED.