[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (B)(1)(e) / Automatic Chemical Controller (ACC) shall function properly.
Critical Automatic Chemical Controller (ACC) was not functioning properly at the time of the inspection. -Observed no power to ACC unit.
Do not operate the pool when the ACC unit is not functioning properly. Ensure that the ACC unit is functioning properly prior to placing the pool back into operation. -Pool operator arrived during inspection and moved plug to working outlet.
3701-31-04 (D)(7)(b) / pH and ORP values shall be displayed.
Critical ORP value was not displayed on the ACC unit -Observed ACC unit inoperable at time of inspection.
Have the ACC unit serviced or replaced so that the ORP value is displayed -Operator arrived during inspection and switched plug to another outlet.


Inspection Information


Facility Type: Spa

[?] Inspection Type: Standard

Inspection Date: 29-April-2022

Comments
The ACC unit was not in operation at time of inspection. Observed new pump motor while performing inspection on Spa. Upon testing chlorine of spa, identified a chemical reaction occurring while testing. Chlorine test immediately clouded over and the sample had a bright purple hue color. This test was accomplished twice for clarity. Pool operator was on site at time of test and said she was getting the same results. The liner of the spa was recently redone in Feb. The spa was immediately drained and closed until further review. Operator stated that she would contact the company that did maintenance on the spa liner.