[?] A summary of the violations found during the inspection are listed below.

3701-31-04 (B)(6)(h) / Required meters and gauges maintained/functional
Required meters and gauges were not maintained or were not functional while the pool is in operation. Observed flow meter not working at time of inspection. Operator noted that plans to install new flow meter are scheduled.
Maintain all meters and gauges in a properly funtioning manner at all times while the pool is in operation.


Inspection Information


Facility Type: Pool

[?] Inspection Type: Standard

Inspection Date: 19-July-2023

Comments
Operator noted that plans to fix flow meter and replace ACC are in place.

Ensure pH is measured and recorded at required frequency as ACC is being replaced.